How Big Are Ohio's Big Data Center Projects?

Ohio data-center capacity figures can describe operational power, critical IT load, future power envelopes or multiple campuses combined. Define the metric before ranking projects.

[ALT TEXT]

What This Graphic Shows

Asking which Ohio data center is “biggest” sounds simple, but public capacity figures often measure different things. A number can describe operational capacity, critical IT load, a future power envelope, or the combined capacity of several campuses.

For example, SiliconReport's governed August 2026 snapshot reports 531 MW of operational capacity for Meta's Prometheus campus in New Albany and 407 MW of operational capacity for Google New Albany. Those figures use the same tracker and the same operational-capacity label, making them more comparable to one another than to many other published numbers.

Microsoft illustrates a different problem. Aterio tracks the company's three Licking County campuses at roughly 869 MW combined—264 MW at Heath, 317 MW at Hebron and 288 MW at New Albany. That is a three-campus development total, not the capacity of a single data center.

STACK Infrastructure uses still another metric for its NAL01 campus in New Albany: 60 MW of critical capacity across two buildings. Critical capacity generally refers to power available to the computing load and should not automatically be compared with a site's total electrical service or a broader campus power envelope.

The lesson is not that capacity data are useless. It is that rankings can become misleading when differently defined numbers are placed in the same column. Before comparing Ohio projects, ask four questions: Is the figure operational or planned? Does it measure IT load or total electrical capacity? Is it for one building, one campus or multiple campuses? And does the source define the metric clearly?

Key Takeaway

A megawatt number is only useful when you know what it measures. Compare like with like: operational vs. planned, IT load vs. total power, and single campus vs. multi-campus totals.

Verification Status:

Verified — Current

Last Verified:

September 15, 2026

Sources

Review the sources used to support this visual.

SiliconReport

Meta Prometheus — New Albany, Ohio

View Source →
SiliconReport

Google New Albany — New Albany, Ohio

View Source →
Aterio

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

July 21, 2026
View Source →
STACK Infrastructure

NAL01 Campus — New Albany, Ohio

View Source →

Explore More

Continue exploring the issue or return to the complete OCG Visual Library.