Explainer

Who Reviews What? Ohio Data Center Approvals

Ohio does not have one universal data-center permit. Zoning, building, environmental, water, power-infrastructure, utility and tax-incentive decisions can be handled by different entities depending on the project.

[ALT TEXT]

What This Graphic Shows

A large data-center project can move through several separate review systems rather than one consolidated approval process.

Local governments may control zoning, land-use approvals, site-plan review and building approvals, depending on the jurisdiction. Ohio EPA administers environmental programs such as air permitting and NPDES wastewater or stormwater permitting when a project's activities trigger those requirements. Ohio's Department of Natural Resources administers separate water-quantity requirements: facilities capable of withdrawing more than 100,000 gallons per day generally must register, and certain new or increased consumptive uses above statutory thresholds require permits.

If serving the project requires a new major generation facility or qualifying high-voltage transmission infrastructure, the Ohio Power Siting Board may have a separate certificate proceeding. Electric utilities and the Public Utilities Commission of Ohio address utility service, tariffs, infrastructure investment, and cost recovery, while PJM performs regional forecasting and transmission planning. These utility/grid processes are not the same thing as local land-use or environmental permits.

Separately, a qualifying data center seeking Ohio's sales-and-use-tax exemption applies through the Ohio Tax Credit Authority under ORC §122.175. Federal reviews can also apply depending on the project – for example, wetlands or other federal jurisdictional issues.

The key point is structural: because oversight is distributed among different decision-makers, a project can satisfy one approval while other reviews are still pending. Understanding who reviews what makes it easier to identify which questions have been answered, which remain open and where the public can participate.

Key Takeaway

There is no single one-stop Ohio data-center permit. Different agencies review different parts of a project, so understanding the approval map is essential to understanding the project.

Verification Status:

Verified — Current

Last Verified:

September 14, 2026

Sources

Review the sources used to support this visual.

Ohio Legislative Service Commission

Ohio Revised Code Section 3791.04 — Submission of plan - approvals

View Source →
Ohio Legislative Service Commission

Ohio Revised Code Sections 303.17 and 519.17 — Zoning certificates

View Source →
U.S. Environmental Protection Agency

Clean Air Act Resources for Data Centers

September 9, 2026
View Source →
Ohio Environmental Protection Agency

NPDES Permits by Type of Permit

View Source →
Ohio Legislative Service Commission

Ohio Revised Code Chapter 1521 — Water Management

View Source →
Ohio Legislative Service Commission

Ohio Revised Code Section 4906.10 — Basis for decision granting or denying certificate

August 14, 2025
View Source →
Office of the Ohio Consumers' Counsel

Quick Facts: Data Centers in Ohio

View Source →
Ohio Legislative Service Commission

Ohio Revised Code Section 122.175 — Tax exemption for computer data center equipment

September 30, 2025
View Source →

Explore More