Natural Gas Is a Major Part of Ohio's Data Center Buildout
Ohio data-center growth is already driving substantial new natural-gas generation, including 736 MW of behind-the-meter gas capacity under construction for Meta and EdgeConneX projects in New Albany.
![[ALT TEXT]](https://cdn.prod.website-files.com/6a4ce2573c5e347b9450aeb1/6aa99f8fe4187d1b36ac878b_ocg_natural_gas_major_part_data_center_buildout.png)
What This Graphic Shows
The original claim that Ohio's entire data-center boom “will run on gas” was too categorical. The evidence does support a narrower conclusion: data-center growth is already driving substantial new natural-gas generation in Ohio.
Cleanview's current behind-the-meter analysis reports that Ohio leads the country in behind-the-meter capacity under construction. Meta and EdgeConneX projects in New Albany account for a combined 736 MW of natural-gas generation under construction.
The Ohio projects are part of a broader national shift. Cleanview identified 59 data centers with roughly 90 GW of announced behind-the-meter generation capacity, with most of those projects announced since the beginning of 2025. Behind-the-meter development is still early: only a small fraction of announced national capacity is operating today, while other projects remain under construction, permitted or at earlier stages.
That does not mean all Ohio data-center electricity will come from natural gas. Many facilities remain grid-connected, and future supply can include utility generation, transmission expansion, nuclear, renewables, storage and other technologies. Project plans can also change before construction or operation.
The more useful question is project-specific: How much new gas generation is actually being built, for which data centers, under what permits, and how will those facilities interact with the regional grid?
Key Takeaway
The evidence supports a major role for natural gas in Ohio's data-center buildout, but not the claim that every new data center will run on gas. Track actual projects, permits and power arrangements.
Verification Status:
Verified — Current
Last Verified:
September 15, 2026
Sources
Review the sources used to support this visual.
Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants
View Source →Ohio Generation Projects — Senate Energy Presentation
Explore More
Continue exploring the issue or return to the complete OCG Visual Library.