Data Centers & AI
/
Economics & Incentives
Explainer

Who Pays for the Infrastructure?

Data centers can require new generation, transmission, substations, distribution equipment, roads, water and sewer capacity. Who ultimately pays depends on what is built, who owns it and how costs are allocated.

[ALT TEXT]

What This Graphic Shows

There is no single answer to the question "Who pays for data-center infrastructure?" Different infrastructure components are funded and recovered under different rules.

A data-center developer may directly pay for project-specific facilities, site work, private substations, behind-the-meter generation, or other dedicated equipment. Electric utilities may build new substations, distribution lines, and service extensions, with costs recovered under utility tariffs or other regulatory arrangements. Ohio's AEP data-center tariff was specifically designed to reduce the risk that residential and small-business customers would bear infrastructure costs associated with exceptionally large new loads.

Transmission is different. PJM plans large regional transmission upgrades and allocates many network-upgrade costs under PJM/FERC cost-allocation rules. In a 2026 FERC filing, PJM testimony stated that most transmission network-upgrade costs associated with large loads are not directly assigned to the large-load customer and instead are socialized within or across transmission zones under the existing methodology.

Local infrastructure can add another layer. Roads, water, sewer, emergency services, and related capacity may be funded through developer agreements, utility fees, local-government spending, or combinations of these depending on the project and jurisdiction.

That is why the useful question is not simply "Does the data center pay?" Ask four questions separately: What infrastructure is needed? Who builds it? Who pays initially? And who ultimately bears the cost after utility, regulatory, and public-finance rules are applied?

Key Takeaway

Follow the cost all the way through: what is built, who funds it first and who ultimately bears the cost can be three different answers.

Verification Status:

Verified — Current

Last Verified:

September 14, 2026

Sources

Review the sources used to support this visual.

Office of the Ohio Consumers' Counsel

Data Center Costs — Who should pay the costs of serving these power-hungry consumers?

View Source →
PJM Interconnection / Federal Energy Regulatory Commission filing

Testimony addressing transmission network upgrade cost allocation for large data center loads

May 7, 2026
View Source →
Office of the Ohio Consumers' Counsel

Quick Facts: Data Centers in Ohio

View Source →

Explore More

Continue exploring the issue or return to the complete OCG Visual Library.